Estimate est_1

draftConfidence 84/100

Total Quote: $2,044.55

Blueprint Preview

Attachment: seed/parking-lot-plan.pdf

Plan Type: parking_lot

Surface: asphalt

Estimate Breakdown

Traffic paint (waterborne): 21.38 gallons @ $48 = $1026.24

Glass beads: 106.88 pounds @ $0.62 = $66.27

Stencil material / consumables: 18 units @ $18 = $324

Labor: $259.35

Markup: $368.69

Draft Response

Hello,

Thanks for sending the plans for Project 1. Based on our review, here is the preliminary striping estimate:

- Traffic paint (waterborne): 21.38 gallons @ $48.00 = $1026.24
- Glass beads: 106.88 pounds @ $0.62 = $66.27
- Stencil material / consumables: 18 units @ $18.00 = $324.00
- Labor: 2.47 hrs = $259.35
- Markup (22%): $368.69
- Estimated Total: $2044.55

Estimated timeline: 2-4 working days after notice to proceed (weather permitting).
Terms: [Insert payment terms / exclusions / warranty].

Regards,
Fast Stripe Co.
StrikePoint