Estimate est_1
draftConfidence 84/100
Total Quote: $2,044.55
Blueprint Preview
Attachment: seed/parking-lot-plan.pdf
Plan Type: parking_lot
Surface: asphalt
Estimate Breakdown
Traffic paint (waterborne): 21.38 gallons @ $48 = $1026.24
Glass beads: 106.88 pounds @ $0.62 = $66.27
Stencil material / consumables: 18 units @ $18 = $324
Labor: $259.35
Markup: $368.69
Draft Response
Hello, Thanks for sending the plans for Project 1. Based on our review, here is the preliminary striping estimate: - Traffic paint (waterborne): 21.38 gallons @ $48.00 = $1026.24 - Glass beads: 106.88 pounds @ $0.62 = $66.27 - Stencil material / consumables: 18 units @ $18.00 = $324.00 - Labor: 2.47 hrs = $259.35 - Markup (22%): $368.69 - Estimated Total: $2044.55 Estimated timeline: 2-4 working days after notice to proceed (weather permitting). Terms: [Insert payment terms / exclusions / warranty]. Regards, Fast Stripe Co.